Skip to Content
718.729.4900

784 Park Avenue

Engineer: Allan Epstein,
Epstein Engineering, PC
A special job was added to this Local Law 11 contract incorporating the replacement of the freight entrance and stairs. And it had to be done in four weeks.

 

In order to accomplish this task on time, the badly deteriorated vaulted sidewalk was ripped up and new steel decking – Q–decking – was installed with I-beams to create a foundation upon which new concrete could be poured. It was then fireproofed and, finally, the new stairs were installed. The building residents were extremely pleased with the quality of the workmanship and the timeliness in which each project was completed.